T1 - Schedule Risk Analysis using a Proposed Modified Variance and Mean of the Original Program Evaluation and Review Technique Model
AU - Sackey, Solomon
AU - Kim, Byung Soo
N1 - Publisher Copyright:
© 2019, Korean Society of Civil Engineers.
PY - 2019/4/1
Y1 - 2019/4/1
N2 - The Program Evaluation and Review Technique (PERT) model uses parameters such as the specified project completion time, mean, and variance to estimate the probability of project completion time. However, this model uses a weighted average and unweighted value in the variance, which is based on six sigma of the mean. Despite many proposed modifications to improve the traditional PERT model, the hidden error in the calculation of the variance and mean of the PERT approach has not been adequately addressed. This error leads to underestimation of the schedule risk. Considering the impact of variance and mean on the probability of project completion times, this study contributes to the improvement of the accuracy of schedule risk estimation by proposing a modified variance and mean of the original PERT model. The original PERT model was first used to estimate the project completion time. However, using the proposed modified model to estimate the completion time, a 95% confidence interval assumption and the corresponding distribution within ±2 standard deviation of the mean and standard or Z values were employed to model the new mean and variance equations. To prove the validity of the proposed modified variance and mean assumptions, we performed a schedule risk analysis through simulation using Oracle Crystal Ball for comparison. The results showed that the proposed PERT model had a better mean error rate of 2.46% as compared to 3.31% of the original PERT model.
AB - The Program Evaluation and Review Technique (PERT) model uses parameters such as the specified project completion time, mean, and variance to estimate the probability of project completion time. However, this model uses a weighted average and unweighted value in the variance, which is based on six sigma of the mean. Despite many proposed modifications to improve the traditional PERT model, the hidden error in the calculation of the variance and mean of the PERT approach has not been adequately addressed. This error leads to underestimation of the schedule risk. Considering the impact of variance and mean on the probability of project completion times, this study contributes to the improvement of the accuracy of schedule risk estimation by proposing a modified variance and mean of the original PERT model. The original PERT model was first used to estimate the project completion time. However, using the proposed modified model to estimate the completion time, a 95% confidence interval assumption and the corresponding distribution within ±2 standard deviation of the mean and standard or Z values were employed to model the new mean and variance equations. To prove the validity of the proposed modified variance and mean assumptions, we performed a schedule risk analysis through simulation using Oracle Crystal Ball for comparison. The results showed that the proposed PERT model had a better mean error rate of 2.46% as compared to 3.31% of the original PERT model.
KW - PERT
KW - probability
KW - project completion times
KW - schedule risk analysis
KW - simulation
UR - http://www.scopus.com/inward/record.url?scp=85060129812&partnerID=8YFLogxK
U2 - 10.1007/s12205-019-1826-z
DO - 10.1007/s12205-019-1826-z
M3 - Article
AN - SCOPUS:85060129812
SN - 1226-7988
VL - 23
SP - 1484
EP - 1492
JO - KSCE Journal of Civil Engineering
JF - KSCE Journal of Civil Engineering
IS - 4
ER -